Spring 2025 improvements are planned for the Wall Street Road on the east end of Clearwater County.
According to a capital projects status update from Clearwater County, 21.1 km of the road is slated for asphalt overlay.
The project has been budgeted at $5,457,000. A contractor procurement process is currently in the works with a closing date of Feb. 13, 2025.
Back in December, however, Erik Hansen, Director of Public Works said neighboring Red Deer County had moved its portion of the road work back to 2026.

Section of the Wall Street Rd. slated for spring 2025 resurfacing. (Clearwater County)
Other projects for the spring include seasonal deficiencies in the newly resurfaced hamlet of Leslieville.
Condor, meantime is also slated to have $10,000 worth of paving work completed within the community this coming summer.
A pair of major bridge rehabilitation projects are also planned, including on the James River Bridge and the North Raven River, each coming in at around $2 million.
Additionally, nearly $5 million has been set aside for gravel road rehabilitation in the county.
–